Fitchburg Commuter Rail Improvements Track, Civil and Signal Project

Somerville to Fitchburg, MA

Advertisement Date 3/22/2013
Pre-Bid Meeting Date & Time April 05, 2013 at 10:00 AM
Bid Opening Date 5/9/2013
Contract Number G67CN03
Class 1 - GENERAL TRANSIT CONSTRUCTION
Project Value $59,990,000.00
DBE Goal 16 %

Scope of Work:

Work on the Fitchburg Commuter Rail Line will consist of improvements to the existing track alignment, construction of new tracks through select segments, new or improved interlockings, a second track through South Acton Station area, a new train control signal system, replacement of Automatic Grade Crossing Warning Systems (AGCWS), upgrade of existing at-grade highway crossing track and roadway surfaces, the retirement of portions of the existing train control signal systems and AGCWS and the demolition of select existing turnouts, crossovers and track segments as indicated. These improvements will be made while the existing commuter line service and freight line service continues to function.

General Contractor Contract Value
Jv: J.F. White / Lm Heavy Civil $57,737,500.00

Notice to Proceed Date: 7/3/2013
Projected Completion Date: 5/31/2016

Bid Responses Bid Amount
Jv: J.F. White / Lm Heavy Civil $57,737,500.00
JV: Barletta/Fischbach and Moore $63,399,430.00
Jv: Balfour Beatty Infrastructure/Balfour Beatty Rail $67,152,790.00
Jv Dragados, S&R, Vias $72,777,033.00
Jv: Walsh/Railworks/Comstock $92,677,760.00

All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.

View Complete Notice to Bidders

View Complete Notice to Bidders (PDF)Comparison of Bids Report for Contract G67CN03 (44.05kb) updated Monday, May 13, 2013

G67CN03 Planholders List    G67CN03 Planholders List (Printer Friendly) G67CN03 Planholders List (Printer Friendly)

Notice
The posting of on-line information on the Massachusetts Bay Transportation Authority Web Page on Massachusetts Bay Transportation Authority construction contracts is being made solely for informational purposes and is subject to change, without notice.

The posting of on-line information shall not be construed as an indication that any person or entity accessing such information is eligible to purchase plans and specifications under M.G.L. c.29, 8B.

The posting of on-line information does not relieve prospective bidders of their obligation to review and become familiar with the Contract Documents, as bid, including, but not limited to, the obligation to inspect plans, specifications and any addenda. The Contract Documents as bid shall supersede and take precedence over any information posted by the Massachusetts Bay Transportation Authority on the Massachusetts Bay Transportation Authority Web Page.

The posting of on-line information does not relieve prospective bidders of their obligation to consult the Central Register published by the Secretary of State's Office pursuant to M.G.L. c. 149 §44J and c.9, §20A for official information concerning any Massachusetts Bay Transportation Authority construction contract. The information published in the Central Register shall supersede and take precedence over any information posted by the Massachusetts Bay Transportation Authority on the Massachusetts Bay Transportation Authority Web page.

Bidders are advised that they should have representation at this tour as no extra visits are planned.