Everett Repair Facility, Fire Protection Upgrade

Everett, Massachusetts

Advertisement Date 4/30/2012
Pre-Bid Meeting Date & Time May 16, 2012 at 10:00 AM
Bid Opening Date 6/27/2012
Contract Number R19CN07
Class 7 - BUILDINGS
Project Value $2,700,000.00
DBE Goal 19 %

Scope of Work:

The Work includes improvements to the MBTA Everett Repair Facility. Work to be performed: New 12” connection to the existing main water line on Broadway. New 10” water line to the Central Storage Buildings. Central Stores Building shall receive a new sprinkler system throughout. A new fire pump is installed in the Central Stores. A new fire protection system installed on the 2nd floor of the Administration building. Work in the Main Repair Building consists of a replacement of sprinkler heads and new sprinklers in unsprinklered areas, including the Diesel Generator Room.

General Contractor Contract Value
Mccourt Construction Co. Inc $2,199,000.00

Notice to Proceed Date: 9/25/2012
Projected Completion Date: 9/25/2013

Bid Responses Bid Amount
Mccourt Construction Co. Inc $2,199,000.00
O'CONNOR CONSTRUCTORS $2,650,000.00
Boston Building & Bridge Corp. $2,791,000.00
R. ZOPPO CO. INC. $2,811,000.00
Wes Construction Corp. $2,935,000.00
Northern Contracting Corp. $3,348,100.00

All PDFs can be viewed with Adobe Acrobat Reader version 4.0 or higher.

View Complete Notice to Bidders

View Complete Notice to Bidders (PDF)Comparison of Bids Report for Contract R19CN07 (51.02kb) updated Tuesday, July 10, 2012

R19CN07 Planholders List    R19CN07 Planholders List (Printer Friendly) R19CN07 Planholders List (Printer Friendly)

Notice
The posting of on-line information on the Massachusetts Bay Transportation Authority Web Page on Massachusetts Bay Transportation Authority construction contracts is being made solely for informational purposes and is subject to change, without notice.

The posting of on-line information shall not be construed as an indication that any person or entity accessing such information is eligible to purchase plans and specifications under M.G.L. c.29, 8B.

The posting of on-line information does not relieve prospective bidders of their obligation to review and become familiar with the Contract Documents, as bid, including, but not limited to, the obligation to inspect plans, specifications and any addenda. The Contract Documents as bid shall supersede and take precedence over any information posted by the Massachusetts Bay Transportation Authority on the Massachusetts Bay Transportation Authority Web Page.

The posting of on-line information does not relieve prospective bidders of their obligation to consult the Central Register published by the Secretary of State's Office pursuant to M.G.L. c. 149 §44J and c.9, §20A for official information concerning any Massachusetts Bay Transportation Authority construction contract. The information published in the Central Register shall supersede and take precedence over any information posted by the Massachusetts Bay Transportation Authority on the Massachusetts Bay Transportation Authority Web page.

Bidders are advised that they should have representation at this tour as no extra visits are planned.