Green Line Transformation Weekly Progress Update: August 6 – August 12
Updated on August 12, 2022
Green Line Transformation
E Branch Train Protection & Track Upgrades | 16-Day Full Access
Friday, August 12
Crews continue to work diligently across the E Branch during our 16-day full access closure. So far crews have replaced over 1,000 feet of track and installed 11% of our GLTPS wayside equipment. Our team has been working closely on alternative service with the Rt. 39 bus, Transit Police on monitoring the flow of traffic within the work zone, and Longwood Collective on their Huntington Ave beautification process.
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Related Projects
GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
Last week, work continued on the following projects:
- E Branch Train Protection and Track Upgrades – 40%
- Green Line Train Protection System – Wayside Installation Ongoing
- D Branch Station Accessibility Improvements — Design Development Phase