Green Line Transformation Weekly Progress Update: February 7 – 12

Updated on February 11, 2021

Steel beams to support the new tracks have been installed on the Lechmere Viaduct

GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.

Last week, crews installed the steel beams that will support the new tracks on the Lechmere Viaduct. The project is now at 54% completion.

Construction will begin on the B Branch Consolidation project on Monday, February 15.

See the February 12, 2021 progress update

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects