Orange Line Improvement Program

New orange line car being tested at Wellington

2015 – 2021

As part of our $8 billion, 5-year capital investment program that began July 1, 2018, we're rebuilding the Orange Line.

This work, including new signal infrastructure, upgrades to our test track, an expanded and upgraded maintenance facility, and an upgraded yard, will result in faster, more comfortable trips on the Orange Line, as well as less crowding on platforms and in stations.

It will also support the all-new, expanded Orange Line fleet of 152 modern, spacious vehicles, ensuring that an additional 30,000 riders per day can take the Orange Line.

Contracts have been awarded for the following projects as part of this initiative:

  • Orange Line signal upgrades: Design started in 2019
  • New Orange Line vehicles: First set of new cars in service August 14, 2019; more in testing
  • Wellington Yard and Maintenance Facility updates: Work started in summer 2017 for the maintenance facility, and spring 2018 for Wellington Yard

The following projects are now complete:

  • Rehabilitation of Orange Line test track: Completed summer 2018
  • Storage track expansions at Wellington Yard: Completed spring 2019

Orange Line Signal Upgrades

The train detection electronics and relays inside the signal bungalow at Forest Hills Station will be replaced.

The analog signal system on the Orange Line will be fully replaced with new, digital infrastructure.

  • Contract awarded: November 2018
  • Projected completion: May 2022
  • Budget: $217 million (total value for Orange Line and Red Line signal upgrades)
  • Status: Preliminary design is under review and development as of June 2019

New Orange Line Vehicles

New Orange Line train at Assembly Station

The Orange Line fleet will be entirely replaced with modern, more efficient, more spacious vehicles by 2022.

  • Contract awarded: 2014
  • Projected completion: 2022
  • Budget: $1 billion (total value for Orange Line and Red Line new vehicles)
  • Status: First set of new cars in service August 14, 2019; more in testing

Wellington Yard and Maintenance Facility Updates

Orange Line train at Wellington

Wellington Yard, the facility where we store and care for Orange Line vehicles each day, will be updated for safer, more efficient maintenance.

Wellington Yard Rebuild

  • Contract awarded: 2018
  • Projected completion: Spring 2021
  • Budget: $102 million
  • Status: 11% complete as of June 2019

Wellington Maintenance Facility

  • ​​​​​​​ Contract awarded: 2017
  • ​​​​​​​ Projected completion: Spring 2021
  • ​​​​​​​ Budget: $76 million
  • ​​​​​​​ Status: 56% complete as of June 2019

Photo Gallery

Contact Information

For all queries and comments related to Orange Line Improvement Program, please contact RedOrangeLineProgram@MBTA.com.

Related Projects

MBTA Improvements

As part of our $8 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

MBTA Improvements

As part of our $8 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more