See Orange Line Work We Completed October 11 – 13

Updated on October 18, 2019

A crew works on track replacement at Downtown Crossing during the October  11 - 13, 2019, weekend shutdown.

During 6 Orange Line weekend shutdowns, we close a section of track from Tufts to Sullivan so crews can bring vehicles and equipment into the central subway tunnel.

These service shutdowns allow our crews to complete work on 2 projects simultaneously—Orange Line Maintenance and Station Brightening—without requiring major long-term service closures. We’re also able to complete this work 11 months earlier than planned.

We thank you for your patience during these closures.

Learn more about Orange Line service changes

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Weekend 2: What We Completed

During the second weekend shutdown, our crews replaced 380 feet of Orange Line track on the southbound side at Downtown Crossing and also replaced the flooring on 2 elevators there.

We also:

  • Painted track and platform areas on State’s northbound side
  • Cleaned platform walls, ceilings, and floors on Haymarket’s northbound side
  • Repaired leaks between Haymarket and North Station

Photo Gallery

Related Updates

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects