See Red Line Work We Completed December 6 – 8

Updated on December 12, 2019

A crew member welds a section of track at Park Street as part of the December 6 – 8, 2019, Red Line weekend shutdown

During 4 weekend shutdowns from November 15 – December 15, 2019, we closed sections of the Red Line to work on track replacement and station improvements. These closures allowed us to complete work at Park Street 4 months earlier than planned and at Downtown Crossing 11 months earlier than planned.

This project, in conjunction with slab replacements we’re working on in 2020, will keep the tracks in a state of good repair and will support the new Red Line vehicles coming into service.

We thank you for your patience during these closures.

Learn more about Red Line service changes

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Weekend 3: What We Completed

Crew members work on track replacement at Park St during the December 6 – 8, 2019, Red Line weekend shutdown

During the third weekend shutdown, our crews replaced 435 feet of track on Park Street’s northbound side.

We also:

  • Painted track and platform areas and installed wayfinding signs on Downtown Crossing’s northbound and southbound sides
  • Repaired ceiling holes and leaks in Downtown Crossing’s Red Line passageways
  • Removed old phone booths at Park Street and Downtown Crossing

Related Updates

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects