See Red Line Work We Completed November 22 – 24

Updated on November 27, 2019

Crew members lay track on the southbound side of Downtown Crossing during the November 22 – 24 weekend shutdown

During 4 Red Line weekend shutdowns, we closed sections of track to work on track replacement and station improvements. These closures allowed us to complete work at Park Street 4 months earlier than planned and at Downtown Crossing 11 months earlier than planned.

This project, in conjunction with slab replacements we’re working on in 2020, will keep the tracks in a state of good repair and will support the new Red Line vehicles coming into service.

We thank you for your patience during these closures.

Learn more about Red Line service changes

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Weekend 2: What We Completed

During the second weekend shutdown, our crews replaced 480 feet of track and 460 feet of third rail on Downtown Crossing’s southbound side.

We also:

  • Installed new tactile warning strips on Downtown Crossing’s northbound platform and Park Street’s southbound platform.
  • Filled 2 ceiling voids in Downtown Crossing’s Alewife passage and removed flooring to prepare for next weekend’s work
  • Removed old phone booths and repaired stair leaks at South Station

Related Updates

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects