Construction 1-Week Look Ahead

Updated on January 14, 2018

Work Hours

The MBTA's contractor, LM Heavy Civil Construction, is working at Wollaston and Quincy Center Stations in 2 shifts:

  • Day shift: 7:00 AM to 3:30 PM
  • Night shift: 9:00 PM to 5:00 AM

On Monday, January 15 (Martin Luther King, Jr. Day), LMH will be working the day shift.

On Sunday, January 14 and Monday, January 15, there will be no night shift work. Night shift work will resume Tuesday evening, January 16 and continue through Friday evening, January 19. Night shift work requires bus shuttles between North Quincy and Braintree Stations.

Weekend diversions will begin next weekend, January 20, with the Red Line shutdown between North Quincy and Braintree Stations.

Current Activities

Wollaston Station on the Red Line closed to passengers on Monday, January 8. The parking lot on site remains open. Free bus shuttle service is now provided to either the North Quincy or Quincy Center Stations.

ActivityStart DateEnd Date
ActivityContinue to set up security and construction work zone fencing around Wollaston StationStart DateMonday, January 15End DateFriday, January 19
ActivityRemove bike cage and foundationStart DateTuesday, January 16End DateThursday, January 18
ActivityRemove and salvage fare collection systemStart DateTuesday, January 16End DateFriday, January 19
ActivityRemove and dispose of station debrisStart DateMonday, January 15End DateFriday, January 19
ActivityMobilize demolition equipment onto station platformStart DateThursday evening, January 18End DateThursday evening, January 18
ActivityDemolish entrance canopyStart DateThursday evening, January 18End DateThursday evening, January 18
ActivityContinue work on Newport Ave. 16-inch water mainStart DateMonday, January 15End DateFriday, January 19
ActivityInstall sewer bypass systemStart DateMonday, January 15End DateFriday, January 19