Wellington Yard, the facility where we store and care for Orange Line vehicles each day, will be updated for safer, more efficient maintenance. This project is part of the Orange Line Transformation Program.

Wellington Yard Rebuild

  • Contract awarded: 2018
  • Projected completion: Winter 2022
  • Budget: $103 million
  • Status: 99% complete

Wellington Maintenance Facility

  • Contract awarded: 2017
  • Projected completion: Summer 2023
  • Budget: $83 million
  • Status: 90% complete

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Why We’re Doing This Work

The Wellington Yard and Maintenance Facility expansion and upgrades will make it easier for crews to move vehicles around the facility, decreasing the time needed for maintenance.

Past Events

View all events

Contact Us

For questions or comments related to this project, please email the Orange Line Transformation team at OLT@mbta.com.

Sign Up for Orange Line Transformation Updates

To get project news delivered to your inbox, sign up for our weekly newsletter.

Related Projects

View all projects

Recent Updates

View all project updates

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Recent Updates

View all project updates