Green Line Transformation Weekly Progress Update: February 21 – 26
Updated on February 26, 2021
GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
Last week, crews began drilling shafts for the foundation of the new Amory St Station on the B Branch. The project is now at 6% completion.
Crews also worked on the Lechmere Viaduct Rehabilitation, installing rebar and other structural reinforcements along the piers. Construction is now 54% complete.