Orange Line Transformation Weekly Progress Update: June 18 - June 24
Updated on June 24, 2022
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
OLT projects will improve safety, reliability, and access for Orange Line riders and the surrounding communities.
Last week, work continued on the following projects:
- Wellington Yard and Maintenance Facility Updates – 91% complete
- Traction Power Substations – 78% complete