Green Line Transformation Weekly Progress Update: June 13 – 18
Updated on June 18, 2021
GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
Last week, work continued on the following projects:
- D Branch Track and Signal Replacement – 90% complete
- Lechmere Viaduct Rehabilitation – 82% complete
- B Branch Consolidation – 63% complete