Green Line Transformation Weekly Progress Update: March 14 – 19

Updated on March 19, 2021

Crews worked on the D Branch Track and Signal replacement in summer 2020, before work was paused for the season.
Crews worked on the D Branch Track and Signal Replacement through fall 2020 before major construction activity was paused for the winter season. Work resumed earlier this week.

GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.

Work resumed on the D Branch Track and Signal Replacement this week, as crews began bringing in construction equipment and replacing signals at Newton Highlands. The project is now at 72% completion.

Work also continued on the following projects:

See the March 19, 2021 progress update

 

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects