Green Line Transformation Weekly Progress Update: May 30 – June 4
Updated on June 3, 2021
GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
Last week, work continued on the following projects:
- D Branch Track and Signal Replacement – 87% complete
- Lechmere Viaduct Rehabilitation – 77% complete
- B Branch Consolidation – 52% complete
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Related Projects
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.