Wollaston Station Improvements

The building facade of the newly renovated Wollaston Station, viewed head on from the new parking lot.

A brand-new, rebuilt Wollaston Station reopened for Red Line service Friday, August 16, 2019.

We closed Wollaston on January 8, 2018, for a $36 million transformation. It was the only station on the Red Line not accessible to people with disabilities and it no longer met safety, flooding, or operational standards—so we rebuilt it from the ground up.

Contract: Awarded June 2017
Budget: $36 million
Status: Station reopened August 2019

Inside the brand-new station, you’ll find accessibility improvements including 3 new elevators, 2 new escalators, 2 additional stairways, and accessible bathrooms.

We’ve also added new pedestrian paths to, from, and inside the new station, including a new pedestrian bridge, and 2 new sets of fare gates to help reduce lines in the station.

Parking Updates

The Wollaston parking lot has been rebuilt and repaved, and it features new lighting, signs and landscaping. As of the reopening, parking prices are:

  • $6 on weekdays
  • $3 Saturdays and Sundays
  • $105 for a monthly pass

Learn more about PayByPhone

Ongoing Work

While we were able to reopen Wollaston for regular Red Line service in August, we’re still working on some final touches at the station, including:

  • Repaving Newport Ave from Brook St to Beale St
  • Repaving Greenwood Ave from Woodbine St to Beale St

Building a Better T

As part of our $8 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Photo Gallery

Take a look back at some of the work we did to rebuild Wollaston.

Related Projects

Contact Information

For all queries and comments related to Wollaston Station Improvements, please contact wollaston@mbta.com

MBTA Customer Support: 617-222-3200

Building a Better T

As part of our $8 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more